METAFRAX INTENDS TO START LAYING FOUNDATION FOR AMMONIA-UREA-MELAMINE FACILITY THIS SUMMER

Main » News Feed » METAFRAX INTENDS TO START LAYING FOUNDATION FOR…

Site preparation lasted for a year in 2017, with an area totalling 20 ha. Subsurface utility engineering is currently underway. Whereas the next stage featuring laying foundation and fixing metal structures is scheduled for summer.

“All works are performed on schedule. A total of 140 people is involved in the construction at the moment, with at least 100 people to join them in a week, owing to the construction expansion. More than 3 thousand people will work on site at the pike period”, – said Vladimir Daut, Director, Metafrax.

Overall project investment is estimated at 950m EUR. Loan agreements on gearing 280m EUR and 27bn RUB are expected to be signed in the days ahead. Project payback period is estimated at 13 years. Gubakha is the site selected for capacities location. Facility commissioning is scheduled for 2021.

The designed capacities for 8-thousand-hour operation per annum will amount to 562k t of urea, 298k t of ammonia, and 40k t of melamine annually. Ammonia production will be based on natural-gas-free technology, with methanol blowout gas used instead. This will ensure reduced emissions and higher energy efficiency.

MORE

SOCAR Carbamide: Urea production can reach 650,000 tons in 2020

SOCAR Carbamide Plant is expected to operate at full capacity in the first half of December 2019, the plant’s Director Khayal Jafarov told reporters on the sidelines of an international conference on the role of the Paris Agreement in climate and environmental change in Baku Nov. 27,Trendreports. The director noted that the volume of urea…


EuroChem and Maire Tecnimont sign memorandum of intent for potential new urea and ammonia plant

EuroChem Group has signed an early works contract for a potential new urea and ammonia production facility, subject to further investment plan approval, at Kingisepp, northwest Russia, with Maire Tecnimont. Under the terms of the agreement, Maire Tecnimont will carry out preliminary engineering and site surveying work at the brownfield site adjacent to EuroChem’s existing…


Fertz major EuroChem nears decision on new ammonia, urea, and methanol plants

KINGISEPP (ICIS)–EuroChem is nearing a final decision on ambitious plans for new ammonia, urea, and methanol plants in northwest Russia to serve international markets, two executives from the Switzerland-headquartered fertilizer group disclosed on Tuesday. The green light for a 1m tonne/year ammonia facility; 1.1m-1.5m tonne/year granular urea plant; and a 1.8m tonne/year methanol manufacturing unit…